Save the Date: June 20th 6:30 Preventive Water Damage Program Presentation

Water damage claims are the most frequent home insurance claim in Charbonneau.  Many can be avoided.  Here are some examples of recent water damage that owners had to deal with:

 

  1. Ice maker water line burst during the night.  The next morning the owners’ new hardwood floors were all buckled and completely destroyed.  It was a nightmare for the owner to get a good contractor to come out and replace her floors and cost many thousands of dollars.

 

  1. The drain hose on a washing machine failed and an entire load of bleach water dumped onto the floor destroying the floor.

 

  1. A hot water tank located in the attic failed and water damaged the ceiling and leaked onto and damaged beautiful antique furniture.

 

To identify problems before they happen, the board is working with our insurance agent and a local plumber to offer optional inspections of our plumbing systems.  Come to an informational meeting and enjoy a nice glass of wine and a variety of meats and cheeses on Wednesday, June 20th at 6:30 pm at Rec Hall C, on Lafayette Dr.

 

Jay Puppo will show a 7 minute slide show of the problem and introduce us to the plumber.  The first 5 owners to sign up for a plumbing inspection will receive high grade stainless steel washing machine hoses to be installed by the plumber.

 

RSVP: Janl4479@gmail.com

Revised = Pool opening schedule – all pools will now open Memorial Weekend

The decision to open only two pools was decided (just a week ago) because of the weather and the cost to open pools even when no one would desire this.

 

Because of the more recent weather (this week) and the forecast for more of the same, the board has decided to open all of the pools this Memorial Weekend.

Enjoy your pool and have a great Memorial Weekend

Pool opening schedule

Pools F/G on Fairway Dr and Pool C on Lafayette will open Memorial Weekend.  Everyone’s pool keys will open all pools so feel free to enjoy these two pools.

The other pools will be open soon and a post will be sent out as soon as the other pools are to be opened.

Update on Wilsonville Storm drain/Sewer Construction

Update on Sewer/Storm drain construction

According to Zachary J. Weigel, Civil Engineer, City of Wilsonville the scheduled construction on Fairway Dr is now delayed until July.

 

 

Come meet your new HOA board members at the monthly meeting on Wednesday May 10th

Results of the ballot for three positions on the Board were announced at the Annual Meeting held at the Country Club, last Monday April 24th.  Ron Reiter was re-elected for another term, Barry Hendrix and Janet McGarrigle will joined the board.  If you would like to come and meet your new board members, a great way to do that is to attend the monthly board meeting at Rec Hall C, on Lafayette St at 10:00 am on May 10th

At the board meeting following the Annual meeting the following officers were elected:

Jan Landis, President,

Secretary, Janet McGarrigle,

Treasurer, Sandie Maki,

Architectural, Ron Reiter,

Landscape Chair, Ralph Martin,

Welcoming Chair, Ty Kuhns,

Communications, Barry Hendrix

Bob Barnum will continue as a member at large and Eric Hoem will continue as Disaster Preparedness

Please also thank Chuck Robertson, Mike Tewell, and Rosemary Ricken for the service as board members for the last few years.  They did a great job and we have all benefited from their dedication to our HOA

 

New information from Zach Weigel on City of Wilsonville Storm drain/Sewer Construction

Email from Zach Weigel:

Good Morning,

 

I wanted to give you an update on the construction schedule for the Charbonneau Utility Repair work as I am sure many of you are wondering why construction has not started yet.  Recently, the City’s contractor requested that the construction schedule be delayed a couple of months to better align with their pipe lining subcontractor’s schedule.  Pipe lining is very specialized work, which is becoming more and more popular as a solution to repairing older pipelines.  As a result, scheduling contractors that specialize in pipe lining is becoming difficult.

 

Instead of starting the construction work now and then waiting until the pipe lining contractor is available, the City has requested the Contractor delay the start of construction to better align with the pipe lining schedule.  This will lessen the amount of total construction time and impacts to the residents.

 

I had been waiting to send a project update until the details of the construction schedule change are resolved with the Contractor, but I realize that we are almost two weeks beyond the original start date.  As soon as the construction schedule is resolved, I will send you an update and provide updated notice to residents within the construction areas.  I apologize for any inconvenience.

 

Thank you,

 

Zachary J. Weigel, PE
Civil Engineer

City of Wilsonville

Check Your Disaster Preparedness Kit for a possible leak of Waterless gel

At our Annual meeting on Monday 4/24, Eric Hoem and Mike Tewell set up a great display of Earthquake information and disaster supplies.  Eric was showing his Quake-Ready Kit to a person interested and found that one of the packets had been leaking.  The small bottles of antiseptic hand cleaner had leaked into the zip bag it was in and destroyed several components, including the First Aid booklet, waterproof matches, and packaged hand wipes, and covering the rest with hand cleaner goo.
Eric contacted Lee Montalvo, the supplier, and he is mailing replacement items to Eric for his kit.  Because of this discovery Eric thought any folks who have purchased a Quake-Ready Kit should think about checking the contents of their kits.  For anyone finding a problem the contact information for the Quake-Ready kit is: Lee Montalvo, 360-791-7746 and lee@quakereadykit.com.

Fairway Drive Work Delayed one week (City of Wilsonville replacement of sewers and storm drains)

You probably already guessed …. The Fairway Dr/Boones Bend Rd has been delayed a week.  I spoke with Zachary (Civil Engineer for the project) today and he stated that they are having a meeting on Thursday and there will more complete information on Friday on the Website http://www.ci.wilsonville.or.us/651/Charbonneau-High-Priority-Utility-Repair   New Start date Monday April 24th

 

Some of you may have received  letters from the city describing  the next area of Charbonneau to be included in the sewer, water and storm drain projects. This April through August the city will be replacing sewers and some storm drains. The project which effects CHOA will be starting on Boones Bend at its first intersection with French Prairie down to Fairway, then up Fairway to 8065 SW Fairway Dr.

Since Boones Bend and Fairway Dr are well traveled roads I thought it would be good to let everyone know about the coming construction.

Construction will start April 17th, there will  likely be no access to Fairway Dr from the French Prairie 1st entrance into Charbonneau, think about taking the 2nd entrance to Charbonneau if you need to visit anyone on Fairway Dr, especially between the hours of 7:00 am and 5:00 pm from April 17th April 24th through August 2017.

There may be a shortage of guest parking during the day on some of Fairway Dr and Boones Bend as those who live on Fairway may need to use the guest parking areas during construction.

Access to more information can be found at http://www.ci.wilsonville.or.us/651/Charbonneau-High-Priority-Utility-Repair

 

2017 Annual Meeting – Important that all attend

Our Annual Meeting is scheduled for Monday 4/24/17 at 7:00 pm at the Charobonneau Country Club.   Please plan to attend this important meeting

Agenda:

  • Introduction of  Current Board Members
  • Election of New Board Members
  • Guest Speaker
  • Minutes from 2016 Annual Meeting for approval
  • Financial Report
  • Updates and Accomplishments
  • Disaster Preparedness
  • Homeowners Open Forum

We will have a raffle and coffee and cookies, so it will be both a good time and an informative time, so be sure to attend

Next area of Charbonneau where the City of Wilsonville will be replacing the sewers and storm drains

Some of you may have received  letters from the city describing  the next area of Charbonneau to be included in the sewer, water and storm drain projects. This April through August the city will be replacing sewers and some storm drains. The project which effects CHOA will be starting on Boones Bend at its first intersection with French Prairie down to Fairway, then up Fairway to 8065 SW Fairway Dr.

Since Boones Bend and Fairway Dr are well traveled roads I thought it would be good to let everyone know about the coming construction.

Construction will start April 17th, there will  likely be no access to Fairway Dr from the French Prairie 1st entrance into Charbonneau, think about taking the 2nd entrance to Charbonneau if you need to visit anyone on Fairway Dr, especially between the hours of 7:00 am and 5:00 pm from April 17th through August 2017.

There may be a shortage of guest parking during the day on some of Fairway Dr and Boones Bend as those who live on Fairway may need to use the guest parking areas during construction.

Access to more information can be found at http://www.ci.wilsonville.or.us/651/Charbonneau-High-Priority-Utility-Repair